Create "Program Document" (Optional)



Phase 1: Setting the Stage • DoubleMCX 2110 Bridge Dashboard

This document defines the functional and architectural requirements of the facility and is sometimes included as part of the initial System Proposal or Contract package prepared by Marketing/Sales.

Important Note for 2110 Projects:
In ST 2110 deployments, the Program Document is rarely truly optional. It is one of the highest-leverage documents in the entire project.

Typical Content

Process

The Program Document must be formally submitted to the client for review, comment, and written sign-off before detailed engineering design begins.

Why This Step Is Critical in 2110 Projects

Aspect Traditional SDI Impact ST 2110 Impact
Room Layout & Cable Pathways Moderate Critical – Affects PTP timing domains and latency
HVAC & Cooling Important Very High – “Thermal Tax” from high-density IP gear
Power & Grounding Standard Critical – Directly affects timing jitter and stability
Future Expansion Nice-to-have Essential – Leaf-spine fabrics are built for scale

Client sign-off on this document helps prevent expensive redesigns later when facility constraints surface during detailed network, timing, and power engineering.